Small Business Resources, Business Advice and Forms from AllBusiness.com

Schools project lagging behind

By Gilbert, Helen
Publication: Supply Management
Date: Thursday, November 16 2006

Procurement delays have caused the ?45 billion Building Schools for the Future (BSF) programme to risk missing targets, an annual report by the Construction Products Association (CPA) has found.

The BSF programme aims to rebuild and revamp 3,500 schools in England by 2020, and under the first

wave, 350 secondary schools should be completed by 2008.

According to the Achievable Targets. Is Government Delivering? report, released by the CPA this month, 39 local authorities had identified projects covering 338 schools by July 2006. But only eight had appointed a preferred bidder and only one scheme has reached financial close.

The Department for Education and Skills (DfES) confirmed the figures and said a longer than expected planning and procurement process at local authority level was behind the delays.

"We will not hand over tens of millions of pounds to local authorities until we are satisfied that the capital projects planned have an outstanding business case and level of design," said a department spokesman. He added many capital projects across sectors fall behind schedule but BSF was getting back on track.

Michael Ankers, chief executive of the CPA, said a clear programme for delivering targets with 'interim milestones' should be set out. This would ensure programmes are delivered efficiently and on time. The report also called for the DfES to collect and publish information on the number of schools that have been built, rebuilt or remodelled outside the central government programmes.

The news comes less than a month after Tim Byles, the government's former national procurement champion, took up the role as chief executive of Partnerships for Schools, which manages the BSF programme. He described the challenge of the BSF project as a "once-in-a-generation opportunity to transform education".

In addition, make sure to read these articles:

  • Slow procurement threatens progress of school buildings
  • Swifter procurement processes are needed if the Building Schools for the Future (BSF) scheme is to survive, says president of the Association of School and ......
  • NEWS: IN BRIEF
  • CPA warning over costs Suppliers are being squeezed by rises in energy and material costs, according to the Construction Products Association. Allan Wilen, economic adviser ......
  • Call and Answer
  • HEADNOTE PENDING LEGISLATION HEADNOTE A bill in a suburban county of Washington could halt construction of new homes. A NEW MEASURE IN PRINCE GEORGE'S COUNTY, ......
  • Cash problems see builders set up new supplier group
  • The construction industry will set up a new advisory group on improving supplier relations after financial problems spelt the end for its predecessor. The Construction ......
  • Certificate level, managerial level, strategic level and TOPCIMA
  • Whether you're attending college, taking a distance-learning course or self-studying, you'll spend some time learning on your own. It's crucial to consider how to manage ......
  • Construction product manufacturers fear business deterioration. (Europe).
  • Construction product manufacturers have seen their business activities disrupted by the aftermath of last month's terrorist attacks on the US. Furthermore, the industry is concerned ......
  • ON THE MOVE
  • * Rob Sykes has become chair of the Chief Executives' Task Force, which provides strategic direction to the nine Regional Centres of Excellence.
  • Certificate level, managerial level, strategic level and TOPCIMA
  • HEADNOTE Julia Brown offers a guide to making the best use of your study time and using the many learning resources that are available on ......
  • Councils challenged to shape up on debt collection
  • Accountants are urging councils to sharpen up their debt collection procedures. A two per cent improvement in council tax collection, from their current performance of ......
  • Whitehall refuses to ditch auctions
  • HEADNOTE E-AUCTIONS The government is standing firm on the use of e-auctions despite another construction organisation condemning them for promoting lowest-price buying. The Construction Products ......
  • E-Tagging construction products. (Handling & Transport).
  • The tremendous advantages of electronic tagging will soon be harnessed by the Construction industry. Long used by the retailing and parcel distribution services, E-tagging represents ......
  • What to do when the campaign is over.
  • When the capital campaign is over, the natural instinct is to rest. But that is the time to evaluate the campaign while laying the ground ......
  • NEWS: IN BRIEF
  • UN suspends supplier The United Nations has suspended Eurest Support Services (ESS) as a supplier of food following allegations it illegally obtained information about a ......
  • Turning browsers into buyers
  • Trading in 2006 will be just as sluggish as 2005, analysts predict. To survive the last leg of the current consumer downturn, and get one ......
  • Setting financial benchmarks as an investment evaluation tool
  • There is a good deal of discussion about financial benchmarks these days. As a general rule, benchmarks are a measuring yardstick for evaluating performance of ......