Concrete On The Wild Side

Pumping concrete for a 5-foot wide sidewalk may sound straightforward, but accomplishing it in an environmentally protected area while reaching the farthest point 1,644 feet away definitely presents unique challenges.

To complete the job, which was located within the 217-acre Yamato Scrub Natural Area in Boca Raton, Fla., pumping contractor M&M Concrete Pumping recently used two Putzmeister Thom-Katt trailer-mounted concrete pumps. Used in an unusual pump-to-pump arrangement, the Thom-Katts placed 80 cubic yards of concrete to construct the long and curving sidewalk.

"The job was brutal," says M&M owner Mike Moberg. "It's incredibly rare to use two trailer pumps in a pump-to-pump approach, especially when pumping a harsh 3/8-inch pea rock mix such an enormous distance. Plus, we had to be extremely careful not to damage any vegetation while pumping along a looping sidewalk path."

On a normal pour, a trailer pump from M&M's 12-unit fleet uses about 200 feet of delivery system. At eight times that distance, this job was an exceptional and complex endeavor.

In addition, keeping ready mix trucks from driving over and disrupting the vegetation was key. Thus, the concrete (supplied by Maschmeyer Concrete of Lake Park) was discharged at the scrub's edge, where the first trailer pump, a model year 1998 TK 50, was positioned. With its maximum 950-psi pressure, that unit pumped concrete 700 feet through 2-inch steel pipe and hose to a second pump, which was set up on a narrow access road inaccessible to ready mix trucks. That second high pressure unit, a bigger TK 70, pumped the mix another 944 feet through larger 3-inch line that tapered to a 2-1/2-inch size, while snaking around sharp bends before reaching the furthest point of concrete placement 1,644 feet away.

Delivery line size proved to be a significant aspect of the complex pumping equation.

"The smaller the line size, the higher the pressure needed," notes Jim Henegar, co-owner of Miami-based Thomas Machinery, the Putzmeister equipment dealer in the area. "As higher pressures force water into the rock, the mix tends to dry out and makes pumping more difficult at such far distances." He adds, "As the concrete would already be stiff from going the long distance from the first pump to the second, M&M's use of a larger line size for the last 944-foot stretch was a key factor in effectively pumping the concrete the final distance."

And all of this had to be accomplished while protecting the environment.

"As the area was environmentally protected, the plants could not be disrupted in any manner," says Moberg. "We could have avoided about 250 feet of delivery system if allowed to make a beeline straight through the scrub."

To address these concerns, the delivery system had to remain within the curving sidewalk forms. In addition, crews could only venture 18 inches outside the forms on either side, paying special attention to ensure no foliage was harmed during the construction.

There were also environmental concerns with priming the pump with grout. As a grout primer was a critical aspect, two yards of a high strength 6,500-psi mix were eventually proposed and allowed. To dispose of the primer without placing it within the scrub's natural habitat or compromising the sidewalk's integrity, crews placed the strong mix as a low 1-inch layer within the overall 5-inch thick concrete walkway.

Constructed under the direction of concrete contractor West Construction of Lake Worth, Fla., the challenging sidewalk was just one portion of a contracted construction project for various sidewalks, small parking lots and informational kiosks for three different scrubs within Palm Beach County. Ultimately, these construction feats will enable visitors to more conveniently view the natural and exotic plant species along with the protected wildlife of this rare ecosystem.

In addition, make sure to read these articles:

  • U.S. Mall Openings Slow While Arab Malls Head Skyward
  • I was shocked to learn — while researching a story for a Georgia magazine — that Gwinnett Place Mall in suburban Atlanta is considered old....
  • You Thought You Had it Tough...
  • When I stepped onto Ocean Ave. in South Beach, Florida last Friday morning I immediately thought I had made a mistake in 1992 when I ......
  • Balancing Work and Life: Goodbye Crackberry?
  • Technology can help entrepreneurs stay in touch — or keep them from letting go.
  • Putzmeister
  • The largest trailer-mounted concrete pump in the world, the BSA 14000, now features a larger 630-hp Cat engine. It is said to have the highest ......
  • Concrete foundation crack repair kit.
  • by Emecole Features: polyurethane crack injection start-up kit comes with enough product to fix up to 30 feet of concrete; kit includes dual cartridges of ......
  • Driving piles near new concrete.
  • Q. How many days should we wait before beginning to piling near a newly placed concrete retaining wall? The wall is 15 feet high and ......
  • Pumps Concrete 197 Feet
  • According to Schwing, the S 61 SX, with a vertical reach of 197 feet 2 inches, is the longest boom pump in the industry. The ......
  • Bigger, Better
  • The largest trailer-mounted concrete pump in the world — the Putzmeister BSA 14000 — just got even more powerful with the addition of a larger ......
  • Building A Florida Waterfall
  • An elaborate and decorative waterfall, created in part with concrete pumping technology, is one of the signature amenities at the Old Palm golf and estate ......
  • Building bridges: we get our feet wet in the name of the environment more than our...
  • When the dispatcher phoned to warn me to bring my hip boots to the church job just outside of town, I should have known I ......
  • Columbus, GA, expands successful, in-house pipebursting.
  • Columbus Water Works (CWW), Columbus, GA, has a dubious distinction. The water and sewer utility is undoubtedly one of the most experienced pipebursting utilities in ......
  • Big Time
  • A continuous concrete pour lasting almost 10 days has been one of the highlights of construction activity on a 190-foot feed mill silo being built ......
  • Pea gravel mix.
  • Q. I'm trying to find some information regarding using a mix that has only 3/8-inch coarse aggregate for a residential slab on grade in a ......
  • Concrete Through The Scrub
  • Nestled in the heart of Palm Beach County, Fla., on the shores of the Intracoastal Waterway, is the quaint town of Hypoluxo. Although a small ......
  • Tall Order
  • After honing their skills on the new 33-story Kilbourn Tower in downtown Milwaukee, Potratz Concrete Pumping, Franksville, Wis., discovered the ideal formula for high rise ......

Starting a Business: Act Bigger Than You Are
Host Hattie Bryant of Small Business School interviews Tere Zubizarreta and coworkers of Zubi Advertising, an advertising agency based in Miami, Florida.