FCC/Necso/ACS jv has been awarded a $23 million contract to construct 1.3 km of line 9 of Madrid metro at Riva in an 8 m-deep cut-and-cover trench in eight months. The project is financed by Tres Cantos, a state-owned enterprise. The contract also includes extensions to the train depot and building of a new electricity substation.
On the Madrid-Barcelona High Speed Railway the Wirth reaming TBM has broken through at Paracuellos after a 2.8 km drive in which the 7 m/day target was often exceeded and a maximum advance of 22.4 m/day was recorded. The roof and sides have be